Activity |
Anticipated Completion Date |
Actual Completion Date |
---|---|---|
File CR-101 |
Jan 31, 2022 |
Jan 26, 2022 |
Notify stakeholders |
Feb 14, 2022 |
Feb 4, 2022 |
Create stakeholder workgroup |
April 1, 2022 |
April 29, 2022 |
Communication systems, resident access, facility policies, etc. |
June 15, 2022 |
September 21, 2022 |
Visitation of Essential Support Persons | Aug 15, 2022 | November 16, 2022 |
Safe and healthy environment | Nov 15, 2022 | |
Disaster plans | April 15, 2023 | |
Review draft rules with ALTSA/RCS leadership |
May 2023 |
|
Conduct informal stakeholder rule review and comment |
June 2023 |
|
Prepare proposed rules and required analyses |
July 2023 |
|
File CR-102 |
Aug 2023 |
|
Notify Stakeholders |
Aug 2023 |
|
Hold Public Hearing |
Sept 2023 |
|
Prepare Concise Explanatory Statement |
Oct 2023 |
|
File CR-103 |
Nov 2023 |
|
Notify stakeholders |
Nov 2023 |
|
Rule Effective |
Dec 2023 |
|
Page Topic:
Disaster Preparedness2